Solar Turbines (Solar) and Whitewater Midstream (Whitewater) selected Flint to install Open Ground Module (OGM) compressor stations across Whitewater’s natural gas pipeline systems throughout Texas.
The standard OGM compressor station configuration for this program consists of two (2) Solar Titan 250 gas turbine-driven centrifugal compressor packages, providing a combined output of 66,000 horsepower (46 MW) per station. Each facility consists of Balance of Plant (BOP) equipment, utility systems, 42-inch, 36-inch, and 30-inch main gas piping, interconnecting process piping, and complete electrical and control systems.
To date, under this program, Flint has installed 27 compressor stations incorporating 54 Solar turbine packages and approximately 1,750,000 HP (1.2 GW) of installed compression capacity across the Whitewater pipeline network.
Whistler Compressor Stations
Big Wells, Del Rio, Rankin, and Waha, TX
The Whistler project scope consists of three (3) greenfield compressor stations comprised of two (2) Solar Titan 250 gas turbine driven centrifugal compressor sets at each station and one (1) compressor station comprised of two (2) Solar Mars 100 gas turbine driven centrifugal compressor sets.
Flint’s project scope includes construction and installation services of the turbine compression equipment, Balance of Plant (BOP) equipment, utility systems, 42”, 36”, & 30” main gas piping, interconnect piping, and electrical.
The multiple compressor station construction was executed sequentially with each site taking approximately 12 weeks.

Client
Solar Turbines
Delivery Method
– General Contractor
Key Features or Awards
– Six (6) Solar Titan 250 Turbines
– Six (6) C75 Centrifugal Compressors
– Two (2) Solar Mars 100 Turbines
– Two (2) C65 Centrifugal Compressors
– 42″, 36″, and 30″ High Pressure Gas Piping
Participating Quanta Companies
– Flint
Whistler Expansion Compressor Stations
Freer, Uvalde, and Ozona, TX
The Whistler Expansion project scope consists of three (3) greenfield compressor stations comprised of two (2) Solar Titan 250 gas turbine driven centrifugal compressor sets at each station.
Flint’s project scope includes construction and installation services of the turbine compression equipment, Balance of Plant (BOP) equipment, utility systems, 42”, 36”, & 30” main gas piping, interconnect piping, and electrical.
The multiple compressor station construction was executed sequentially with each site taking approximately 12 weeks.

Client
Solar Turbines
Delivery Method
– General Contractor
Key Features or Awards
– Six (6) Solar Titan 250 Turbines
– Six (6) C75 Centrifugal Compressors
– 42”, 36”, and 30” High Pressure Gas Piping
Participating Quanta Companies
– Flint
Matterhorn Express Compressor Stations
Waha, Rankin, Eden, and Florence, TX
The Matterhorn Express project scope consists of four (4) greenfield compressor stations comprised of two (2) Solar Titan 250 gas turbine driven centrifugal compressor sets at each station.
Flint’s project scope includes construction and installation services of the turbine compression equipment, Balance of Plant (BOP) equipment, utility systems, 42”, 36”, & 30” main gas piping, interconnect piping, and electrical.
This multiple compressor station construction scope was executed sequentially with each site taking approximately 12 weeks with a demobilization to set equipment at Agua Dulce compressor station.

Client
Solar Turbines
Delivery Method
– General Contractor
Key Features or Awards
– Eight (8) Solar Titan 250 Turbines
– Eight (8) C75 Centrifugal Compressors
– 42”, 36”, and 30” High Pressure Gas Piping
Participating Quanta Companies
– Flint
Agua Dulce Compressor Station
Agua Dulce, TX
The Agua Dulce project scope consists of one (1) greenfield compressor station comprised of two (2) Solar Titan 250 gas turbine driven centrifugal compressor sets.
Flint’s project scope includes construction and installation services of the turbine compression equipment, Balance of Plant (BOP) equipment, utility systems, 42”, 36”, & 30” main gas piping, interconnect piping, and electrical.
This compressor station construction was executed in approximately 12 weeks with a demobilization to allow completion of Matterhorn Express Compressor stations.

Client
Solar Turbines
Delivery Method
– General Contractor
Key Features or Awards
– Two (2) Solar Titan 250 Turbines
– Two (2) C75 Centrifugal Compressors
– 42”, 36”, and 30” High Pressure Gas Piping
Participating Quanta Companies
– Flint